Checking the status of the previous tree content synchronizations

You can check the status of these previous tree content synchronizations:

To check the status of the previous tree content synchronizations:
  1. Log in to Optimizely.

  2. For Optimizely version 11: in the main panel, in the top navigation bar, select the Admin tab. Then, in the left hand-side panel, select the Admin subtab. Next, in the Scheduled jobs section, select the XTM Schedule Tree Content Synchronization option. Finally, in the XTM Schedule Tree Content Synchronization screen, select the History tab.

    For Optimizely version 12: in the main panel, in the top navigation bar, select the Admin tab. Then, select the Scheduled jobs subtab. In the Scheduled jobs list, select XTM Schedule Tree Content Synchronization. Finally, in the left hand-side panel, select History.

  3. In the History tab screen, you see a table containing these details about past tree content synchronizations:

    • the date and time at which the synchronization took place.

    • how long the synchronization process took.

    • status of the synchronization. The possible options are:

      • Succeeded.

      • Failed.

    • message about the synchronization status.

    • server. This information is only displayed for Optimizely version 11.